国产在线一区二区三区,高清一区二区三区,国产成人99久久亚洲综合精品,国产精品人妻无码一区二区三区

Service Hotline: 18652225078 0516-83055196

Installation and disassembly of construction hoist

Release time: 2021-05-29 Visited: 426

Preparation before installation

1 The installation site should have sufficient power supply, and must be equipped with a power box dedicated to the elevator. Each cage should be controlled by a switch. The current of the power supply fuse should be referred to the elevator performance parameter table;

2. The dedicated power box on the construction site should be directly introduced from the transformer room on the construction site, and the distance should not exceed 25m. Generally, one cable is used, or each cage can be connected by one cable. The cable section specification is larger than that of the main cable of the cage. One size bigger. If the distance exceeds 25 meters, the cross-sectional area of the cable should be appropriately increased;

3. Appropriate lifting equipment and installation tools should be available

4. There should be roads and sites for transporting and stacking elevator parts;

5. The user should make the basis as required

6. Determine the connection plan between the attached wall frame and the building, and prepare embedded parts or fixed parts as needed

7. According to user needs, bring your own platform accessories, such as bridge boards, safety railings, platform landing doors, etc.

8. According to relevant regulations and requirements, set up a grounding device to ensure that the grounding resistance is not greater than 4Ω;

9. According to relevant regulations and requirements, the maximum deviation of the site power supply voltage is ±5%, and the power supply is not less than the total power of the motor

10. If the construction site is powered by a generator, it must be equipped with reactive power compensation equipment to ensure power quality

11. The construction site should be equipped with a suitable leakage protection switch.

Parts that need to be provided by the user

1. The lift foundation made according to the requirements, and some 2~12mm thick steel gaskets, used to pad into the chassis and adjust the verticality of the rail frame;

2. Dedicated power box and connecting cable equipped as required;

3. A cable with a suitable specification is used to connect the dedicated power box and the power box of the elevator. The length is generally not more than 25 meters, and the shorter is better.

4. Select the connection scheme of the attached wall frame, prepare the connecting bolts and embedded parts

5. In addition to the special tools provided with the machine, the user needs to prepare a set of installation tools.

Installation safety requirements

1. The installation site should be cleaned up and enclosed with sign poles, etc., and non-workers are forbidden to enter

2. Prevent objects from falling above the installation site, and safety nets should be added when necessary

3. During the installation process, the installation must be carried out by a professionally qualified installer, and at the same time, a dedicated person shall be responsible for the unified command

4. When the lift is running, the head and hands of the personnel must not be exposed outside the safety fence of the cage, let alone outside the driver's cab

5. Don't forget to tighten the link bolts of the standard section and the wall bracket

6. If someone is working on the rail frame, attached wall frame or under the cage, never start the lift. When the cage is raised, it is strictly forbidden to enter the outer cage.

7. All parts on the hanging cage must be placed stably, and the safety fence must not be exposed

8. When using booms for installation, overloading is not allowed. The booms are only used to install or disassemble parts of the elevator, and not for other purposes.

9. Do not move the cage when there are hanging objects on the boom

10. Installation personnel should follow the safety requirements for aerial work, including wearing helmets, safety belts, and non-slip shoes. Do not wear loose clothes and wear work clothes to avoid being caught in moving parts and causing safety accidents.

11. When operating the elevator during installation, the operating box must be brought to the top of the hanging cage, and operation in the hanging cage is not allowed

12. Before starting the hoisting cage, a comprehensive inspection should be carried out to eliminate all hidden dangers of insecurity.

13. During installation and operation, it must be loaded according to the rated load of the elevator, and overload operation is not allowed

14. Installation operations cannot be carried out during thunderstorms, snowy days, or severe weather with wind speeds exceeding 13 m/s

15. When the elevator is running, firstly ensure that the grounding device is connected to the metal structure of the elevator, and the grounding resistance is not greater than 4Ω

16. The numbers of the transmission trolley and the cage must be the same

17. All parts must use the original parts provided by our company, otherwise there will be safety hazards

18. Without the permission of the company, the electrical wiring of the lift shall not be changed

19. Installation is strictly prohibited at night or after drinking

20. The verticality of the guide rail frame must be checked as required for each installation of the attached wall

21. Lubricate as required after installation

国产免费色情网站入口大全 | 波多野结衣乳巨码无在线观看0 | 在线观看国产高清视频 | 67194熟妇在线观看 | 欧美精品无码成人A片九色播放 | 91久久国产精品熟女线看 | 国产乱码精品一区二区三区Av | 国产村偷农村妇女免费视频 | 国产在线视频一区二区 | 四川少妇BBBBBB爽爽电影 | zv中文字幕乱码在线看 | 国产精品.XX视频.XXTV | 丁香婷婷麻豆草草视频 | 91啊轻点灬太粗太长了岳 | 国产精品扒开腿做爽爽爽视频 | 欧美激情视频一区二区三区 | 超碰爆艹乱伦黑人巨吊艹大逼 | 影音先锋av在线资源 | 日本乱偷中文无码字幕 | 近親相姦中出し親子白木优子 | 亚洲成国产人片在线观看 | 丰满又紧又爽又丰满视频 | 久久久国产精品人人片 | 亚洲精品秘 一区二区三小 91麻豆精品久久久久蜜臀 | 真人无遮挡毛片免费视频 | 中文字幕精品在线观看 | 无毛逼久久久久久久久久 | 免费在线观看黄色小说 | 国产一级a毛一级a看高清视视频 | 欧美成人A片久久久电影 | 99久久久无码国产精品免费四季 | 2019国产精品 | 亚洲午夜成人天堂精品 | 国产午夜麻豆影院在线观看 | 精品乱码一区内射人妻无码 | 欧一美一性一交一大一片 | 情趣美女色诱视频网站免费观看福利 | 成人午夜啪免费视频在线观看软件 | 精品国产丝袜自拍人妻 | 中国女人的j 视频 污 | 都是激情中文字幕淫荡人妻 |